• L&T-Sargent & Lundy
  • L&T-Sargent & Lundy

4x120 MW Riyadh PP-8 Ext-III SCPP Project, Saudi Arabia



  •  

    Name of Project : 4x120 MW Riyadh PP-8 Ext-III Simple Cycle Gas Based Power Project at Riyadh, Kingdom of Saudi Arabia (KSA)

    Owner : Saudi Electricity Company (SEC), Kingdom of Saudi Arabia

    Client : Al-Toukhi Company for Industry, Trading and Contracting (TIT), Kingdom of Saudi Arabia

    Capacity : 4x120 MW

    L&T-S&L’s scope : 

    • Complete Basic and Detail engineering services as per SEC Specifications
    • Interface engineering for interface with existing 380 kV substation
    • HAZOP Study

    Configuration : Four (4) GE make Frame 7FA Gas Turbine Generators (GTGs) in simple cycle mode

    Key Technical Features :

    • GTG of capacity 120 MW each dual fired type
    • Fuel gas pressure reduction skid, fuel oil system comprising of three (3) bulk diesel oil tanks, four (4) diesel forwarding pumps with filtration systems to be located in existing fuel oil forwarding shade
    • Two (2) instrument air compressor and instrument air system, gas turbine building, battery room, transmission system room, fuel management skid, hydrogen plant

    Fuel : Natural Gas/Fuel Oil

    Year of commissioning : 2008