• L&T-Sargent & Lundy
  • L&T-Sargent & Lundy

50 MW CCPP Pipavav Power Plant, Gujarat, India



  •  

    Name of Project : 50 MW CCPP Pipavav Power Plant, Kovaya, Gujarat, India

    Owner/Client : Gujarat Cement Works, Pipavav, India

    Capacity : 50 MW

    L&T-S&L’s scope : Complete Basic and Detail engineering services

    Configuration :

    • One (1) EGT make Frame 6B Gas Turbine Generator (GTG) of 35 MW capacity
    • One (1) L&T make Heat Recovery Steam Generator (HRSG)
    • One (1) Alstom make Steam Turbine Generator (STG) of 18.5 MW capacity

    Fuel :  

    • Gas turbines are primarily fired with Naphtha. HSD is used for startup and shutdown
    • HRSG at exhaust of GTG is provided with provision for auxiliary firing with naphtha when the GTG is down

    Year of commissioning : 2000