Name of Project : 2x150 MW PACO Power Plant, Panama, Central America
Owner : Minera Panama S.A, Central America
Client : SK Engineering & Construction Co., South Korea /Sargent Lundy, USA
Capacity : 2x150 MW
L&T-S&L’s scope : Complete Basic and Detail Engineering for EPC of entire plant
Configuration :
- Two (2) Seentec-Make Boilers (Subcritical)
- Two (2) SKODA-Make Steam Turbine Generator (STGs)
Key Technical Features :
- Pulverized coal fired Subcritical Boiler
- 150 MW Steam Turbine Generator: tandem compound, reheat, condensing turbine
- Sea water based Flue Gas Desulphurization (FGD) system for SOx emissions control
- Selective Catalytic Reduction (SCR) unit under Boiler scope for NOx emissions control
- Baghouse for flue gas dust collection
- Once through seawater based CW system
- Topping Desuperheater in feed water circuit enhancing cycle efficiency
- Dry bottom ash handling system
- Thermal Desalination plant for sea water
- Design experience for a high rainfall zone plant (approx. 4 to 5 meters of annual average rainfall) with necessary rain-water harvesting facilities
- Gas Insulated Switchyard (GIS)
- Twin Flue Chimney
Fuel : Coal
Year of commissioning : 2016