Name of Project : Relocation of existing equipments and space planning for CCPP conversion for 790 MW SCCP plant
Owner/Client : International Atlas Energy Sdn. Bhd, Malaysia
Capacity : 790 MW
L&T-S&L’s scope :
- Efficiency improvement by converting to CCPP
- Conceptual study and Configuration Study
- Complete Engineering for relocation of equipment, pipes and cables, etc.
- Preparation of procurement specification
- Bill of Material (BOM) generation for the pipes, cables, concrete and steel etc.
- Planning of space required for pipe rack for steam and power cycle pipes and cables around HRSGs upto STGs
- Site Supervision
Configuration : Three (3) Siemens make Gas Turbines (GTs)
Key Technical Features :
- Three Siemens V94.3 A Gas Turbine of capacity 264 MW each
- Siemens Generator rated 310 MVA, 15.75 kV
- Main Fuel: Natural Gas
- Backup Fuel: Gas Oil
- Unit Efficiency: Above 39%
- Air Cooled CCW and Lube oil Coolers
Fuel : Natural Gas
Year of commissioning : Re-commissioned in 2013