3190 MW Qurayyah CCPP Project (1890 MW SCPP + 1300 MW conversion), Saudi Arabia



  •  

    Name of Project : 3190 MW Qurayyah Combined Cycle Power Project (1890 MW SCPP + 1300 MW conversion), Kingdom of Saudi Arabia

    Owner : Saudi Electricity Company (SEC), Kingdom of Saudi Arabia

    Client : Consortium of Arabian Bemco & Doosan Heavy Industries/Sargent & Lundy, USA

    Capacity : 3190 MW

    L&T-S&L’s scope : Basic Engineering (part) and Detail Engineering Services for the EPC of entire plant

    Configuration :

    Combined Cycle Power Plant consisting of Five (5) blocks, each with:

    • Three (3) GE make 7 FA Gas Turbine Generators (GTGs)
    • Three (3) Doosan make Heat Recovery Steam Generators (HRSGs)
    • One (1) GE make TC2F-34.5" - LSB Steam Turbine Generator (STG)

    Key Technical Features :

    • Fifteen (15) GE 7 FA GTGs of capacity 126 MW each
    • Fifteen (15) Triple Pressure, Vertical Type HRSGs
    • Five (5 ) STGs-D11 of capacity 260 MW each
    • Fuel Gas Compressors (6x30% capacity)
    • Thermal Desalination Plant (3x50% capacity)
    • Sea water once through cooling water system with intake & outfall arrangement
    • Hypochlorite Generation Plant (4x50% capacity)
    • Demineralization Plant
    • Compressed Air System
    • Turbine Lube Oil Storage, Forwarding and Purification System
    • Chemical Storage, Forwarding & Dosing System
    • STG bearing oil Seal Air System
    • Hydrogen Generation Plant
    • Remineralization Plant
    • Waste Water Neutralization Plant
    • Plant Nitrogen Purging & Preservation System
    • Fire Protection system

    Fuel : Natural Gas/Fuel Oil

    Year of commissioning : 2014